AquaDam® Installation and Removal Specifications

The AquaDam® is an innovative, water-filled cofferdam that’s valuable for temporary flood control, construction work, water storage and many other applications. Installing and removing this water barrier is a straightforward process to complete.

AquaDam® Installation: Step by Step

The dam installation process will vary based on the site, but there are five general steps:

  1. Receive the AquaDam. AquaDams will ship rolled up like a carpet. After delivery, the AquaDam® must be placed at the top of the starting bank. The height and length specifications will influence the weight of the rolled-up dam. The number of laborers needed is based on the size of the AquaDam® system that will be installed for the project.
  2. Unroll the AquaDam. The rolled-up AquaDam® must be unwrapped before unrolling. After unwrapping, unroll the dam down the starting bank into the water to expose the two fill tubes. The fill tubes are the plastic material coming out of the woven material at the start of the AquaDam.
  3. Connect the pumps. Connect pumps to the 3″ layflat fill-hoses, or run personal hoses into the two fill tubes that create the watertight, side-by-side inner sections of the AquaDam. To prevent tube damage, pad any hoses or pumps inserted into the fill tubes. 
  4. Turn on the pumps. Pump water evenly and equally into the water-tight chambers.
  5. Stop the pumps at the right time. When the AquaDam® reaches its rated height when measured at the lowest point of the path, stop the pumps. Overfilling the dam may cause breakage. Underfilling by 4 to 6 inches can account for low spots in the water.

AquaDam® Removal: Step by Step

Water-filled cofferdam removal is straightforward. Complete the installation process in reverse through the following steps:

  1. Re-water the work area. The water on either side of the AquaDam® must reach the same level before removal. Even water levels on either side will bring the AquaDam’s net force to 0.  
  2. Pump water out of the AquaDam. Pump or siphon water out of the AquaDam® with an electric sump pump or a suction hose for external pumps. Insert equipment into the AquaDam® fill tubes with padding to prevent damage to the inner tube.
  3. Set the AquaDam® onto its wooden core. Only begin this step once the water level inside the dam is below water level. At this point, the dam will float. Use man or machine power to set the AquaDam® on its wooden core on the end opposite the fill-tube openings. 
  4. Roll up the AquaDam. Start rolling up the AquaDam® and pulling the rolled section up the bank. As the dam pulls out of the water, any remaining water inside will drain out through the fill tube openings. Continue pulling and rolling until the dam is completely rolled up.

Before starting the AquaDam® removal process, assess the installation site for factors like flowing water, stream obstructions and lack of access. In these cases, the AquaDam® may not be reusable following removal.

Learn More About the AquaDam

The AquaDam® can be a helpful tool for many applications. The AquaDam® support team is here to assist you — fill out this contact form today with any questions.

Frequently Asked Questions

What are the step-by-step processes for installing an AquaDam?

Installation involves five key steps: (1) Receive the rolled-up AquaDam and place at the starting bank; (2) Unwrap, tie of start end to and anchor on shore, and unroll down the bank into water to expose fill-tubes; (3) Connect pumps to the 3″ fill-hoses sticking out the fill-tubes; (4) Turn on pumps to fill water evenly into chambers to avoid uneven stress; (5) Stop pumps when dam reaches ending bank and has reached its rated height at the lowest point. The straightforward process requires no welding, bolting, or complex assembly. Overfilling can cause damage, and under-filling may lead to instability. Installation timing varies by pumping power, site conditions, and dam size, but most installations can be completed within hours with adequate pumping capacity.

What should be considered before beginning installation?

Before installation, assess the site conditions: (1)What is the maximum controllable water depth within the deployment path, over the duration of the project? (2)Where will the AquaDam start and end? (3) What water source will be used for filling? (4) Are pumps and equipment available and in working order? (5) Is there adequate crew and equipment access? (6) Have permits been obtained if required? Planning these details before receiving the AquaDam ensures smooth installation without delays. The deployment path should be cleared of obstructions to ensure a proper seal. Clear any debris or sharp objects that could puncture the geotextile outer material.

What are the step-by-step processes for removing an AquaDam?

Removal involves four key steps: (1) Re-water the work area until both sides are level (bringing net force to zero) to make removal safe; (2) Pump or siphon water down using pumps with suction hose; (3) Attach the closed end of the AquaDam onto a sturdy wooden core, after the unit begins to float from the water level dropping; (4) Slowly roll up the dam while pulling it up the bank, allowing remaining water to drain out through fill-tubes. This controlled process, when done correctly, can prevent damage and allow potential reuse. The critical element is re-watering the work area beforehand to eliminate pressure differential—attempting removal while one side is seeing a significantly higher load can create unsafe conditions.

What factors determine whether an AquaDam can be reused after a project?

Re-usability depends on the condition of the dam after installation and removal. Before removal, assess: (1) Are there any visible punctures or damage to the geotextile? (2) Is there flowing water, obstructions, vandalism, or complications during installation/operation? (3) Will the AquaDam be installed in the same body of water? (4) Is there room along the ending bank to remove the dam? Careful installation practices, having a removal location, and slow but controlled removal will maximize the reuse potential. However, reuse isn’t guaranteed—if damage occurs during a project, the dam may not be serviceable for future use. This is why proper installation technique and careful site assessment are important considerations in the project planning process.

What training or expertise is needed to install and remove AquaDams?

Installation and removal don’t require specialized engineering training, but proper understanding of the procedure is essential which can be obtained through a “User’s Guide”. The five-step installation process is straightforward but requires attention to detail: even filling, avoiding overfilling, using adequate pumping capacity, and proper site preparation. Removal requires understanding the importance of re-watering before beginning. Most crews with basic construction experience can be trained quickly to install and remove AquaDams safely. Many operators learn quickly through hands-on instruction and experience. For complex projects, working with experienced AquaDam operators ensures optimal results and maximizes re-usability Training materials and on-site support are available through AquaDam specialists.

AquaDam